December -
Aerial view
-
December -
View of the substation
-
December -
Flushing oil lines on the turbine deck with jumper hoses
-
December -
Continuing to perform IO checks on elevation 358.0 (photo courtesy of MWH)
-
November -
Installation of the air and oil piping
-
November -
Cleaning the Unit 1 bulb nose flange
-
November -
Installing the oil head extension shaft (photo courtesy of MWH)
-
November -
Backfilling the underground sanitary drainage tank in the recreational area
-
October -
Excavating material from the tailrace
-
October -
Grinding off the lift lugs on the runner blades in Unit 2
-
October -
Gantry crane support beam being installed on the lifting jacks (photo courtesy of MWH)
-
October -
Megger testing the stator and rotor (photo courtesy of MWH)
-
September -
Installation of the Unit 2 stator
-
September -
Preparing upstream shaft flange for Unit 3 rotor assembly
-
September -
Downstream side of the powerhouse roof and Unit 2 stator
-
September -
Installing the first runner blade in Unit 3 (photo courtesy of MWH)
-
August -
Electricians wiring the Unit 2 bearing oil hydraulic power unit
-
August -
Preparing to install the Unit 1 stator into the bulb turbine housing area
-
August -
Installing the Unit 1 rotor
-
August -
Control room station installation
-
July -
Aerial view
-
July -
Aerial view
-
July -
Setting a runner blade into the runner hub
-
July -
Excavating the tailrace channel
-
June -
Millwrights installing the O-ring on the face of the Unit 2 distributor flange
-
June -
Using the sluice gate to raise the downstream pool (photo courtesy of MWH)
-
June -
Moving the runner blades to the powerhouse roof (photo courtesy of MWH)
-
June -
Installing the bottom half of the discharge ring in Unit 1
-
May -
Excavation along the downstream and riverside areas of the cofferdam
-
May -
Concrete being placed for the sheet piling cap (photo courtesy of MWH)
-
May -
Placing forms and bracing for landside closure structure placement (photo courtesy of MWH)
-
May -
Concrete pour for landside closure structure placement
-
April -
Approach channel cofferdam breached
-
April -
Dry excavation along the upstream cofferdam
-
April -
Controlled fill of the cofferdam interior (intake)
-
April -
Testing the log grabber (photo courtesy of MWH)
-
March -
Aerial view
-
March -
Controlled filling of the cofferdam on the intake
-
March -
Installing diesel generator tank and perforated pipe (photo courtesy of MWH)
-
March -
Installing H-frame on top of the landside entrance building
-
February -
Millwright assisting with the installation of the Unit 3 shaft
-
February -
Electrician is terminating cable in the cabinet for the GIS (gas insulated switchgear)
-
February -
Preparing to transport the Unit 1 lower discharge ring to the powerhouse roof
-
February -
Working on alignment and fit-up of the Unit 1 distributor
-
January -
Cleaning Unit 1 stay cone flange
-
January -
Pulling and tensioning 138kV cables from the 138kV substation frame
-
January -
Unit 3 bulb nose installed in the powerhouse
-
January -
Bulkhead gate lifting beam and bulkhead gates