Deshler 2nd Source Reinforcement Project

AMP Transmission (AMPT) is proposing the Deshler 2nd Source Reinforcement Project to improve reliability for the customers in the Village of Deshler and surrounding areas.

Project Details

The Deshler 2nd Source Reinforcement Project involves the expansion of the 69/12-kV Bremer Substation in Deshler and the addition of a new 69-kV transmission line (approximately 12 miles) between the Bremer Substation and the new First Energy/ATSI Sand Ridge Substation in Weston, OH.

Stakeholder Engagement

AMPT is holding an in-person Open House from 4:00 p.m. to 7:00 p.m. on Monday, April 29, 2024, at the American Legion located at 505 South Stearns Avenue in Deshler.

The community will be able to view detailed maps and talk with team members about the proposed study segments and Project.

The community is also invited to provide their contact information and public comments regarding the proposed study segments via email to AMPT at [email protected].