December -
Sections of the discharge rings staged on the powerhouse roof deck
-
December -
Log grabber function testing
-
December -
Installation of the Unit 3 distributor
-
December -
Unit 3 distributor staged on the powerhouse roof deck
-
November -
Aerial view
-
November -
Formwork and rebar for the final downstream landside entrance ramp
-
November -
Transmission line installation from Tower Structure S002 to H-frame
-
November -
Removal of the cofferdam emergency flooding structure
-
October -
Controlled fill of the cofferdam
-
October -
Setting the inner gate barrel onto the turbine shaft
-
October -
Status of the trash rack panel installation
-
September -
Aerial view
-
September -
Assembly of the trashrake
-
September -
Removing the batch plant
-
September -
Concrete activities for the riverside closure structure
-
August -
Decommissioning and grouting lower ring wells on the riverside intake wall
-
August -
Rooftop view of elevation 305' prep for subdrain floor pour
-
August -
Setting the Unit 1 emergency closure gate HPU bridge into place
-
August -
Bulkhead gate seal retention bar installation
-
July -
Aerial view
-
July -
Carpenters constructing forms for the sheet pile concrete cap on the intake
-
July -
Concrete finishing of the sub drain floors EL 305
-
July -
Removing the centering cone from the Unit 3 BTH assembly
-
June -
Cable tray installation
-
June -
Second stage concrete placement for draft tube bulkhead
-
June -
Lowering the first transformer into the powerhouse
-
May -
Aerial view
-
May -
Concrete placement for Roof Slab 1
-
May -
Rebar and concrete formwork for the trash trough on the riverside closure structure
-
May -
View of the bulb noses
-
April -
Carpenters installing an expansion sleeve for the sheet pile cap
-
April -
Rebar placement for the closure structure
-
April -
Formwork and concrete placement for the fascia wall
-
April -
Downstream view of the Unit 1 bulb turbine housing
-
March -
Boating personnel to the site due to flooding inundating access to the powerhouse
-
March -
View of the high river water inundating access to the powerhouse
-
March -
Status of the second stage embed for bulb turbine housing stay cone 1
-
March -
Concrete placement on the landside upstream fascia wall
-
February -
Aerial view
-
February -
Installing steel reinforcement for the closure structure's fascia wall
-
February -
Offloading one of the runner hubs
-
February -
Morsey making concrete pour
-
January -
Load testing the powerhouse crane 2
-
January -
Staging of the inner gate barrels
-
January -
Work continues on the emergency closure gate and draft tube bulkhead gate
-
January -
Placing formwork for the second stage concrete BTH-SC embedment