December -
View of the tailrace channel during Unit 3 trial run (photo courtesy of MWH)
-
December -
Removing the temporary roof covers over the Unit 1 turbine gallery hatch
-
December -
Pipefitters welding the new oil supply head pipe supports on the Unit 2 generator access hatch cover
-
December -
Painting the powerhouse roof with the polyurethane waterproof coating
-
November -
View of the log grabber and blockhead slots
-
November -
Removing guide bearing shell half for Unit 3
-
November -
Cleaning off the Unit 3 bulkhead gates while removing it from the intake
-
November -
Installing fall protection monorail
-
October -
Inspecting the Unit 3 water passage before closing the discharge ring
-
October -
Lifting the access hatch cover for removal
-
October -
View of the powerhouse roof deck (intake)
-
October -
Demobilizing Tent 1 in Spoil Area 4
-
September -
Installing water tight electrical fitting on the powerhouse crane
-
September -
Grouting the recreational area riprap walkway
-
September -
Performing check outs for Unit 1 bearing oil system (photo courtesy of MWH)
-
September -
Pipefitter modifying the Unit 3 oil head piping
-
August -
Concrete finishing for the fishing pier walkway
-
August -
Air lancing log grabber rails in preparation for grout
-
August -
Performing IO checks for the emergency gate
-
August -
Commissioning team performing a walkdown of the Unit 2 governor system
-
July -
Fishing pier walkway being prepped for concrete placement
-
July -
Electricians testing the gantry crane used for unwatering pump removal
-
July -
Installing the permanent seal for the Unit 3 transformer roof hatch
-
July -
Installing the permanent security fence
-
June -
Pipe fitters installing Unit 3 cooling water screens
-
June -
Millwrights installing Unit 3 servomotor
-
June -
Carpenters beginning to install fishing pier walkway forms
-
June -
Performing load test for the log grabber
-
May -
Preparation to move Unit 3 servomotors to the powerhouse
-
May -
Millwrights in the Unit 3 bulb turbine housing installing shaft seals
-
May -
View of the Unit 2 baffle plate installation
-
May -
View of the installed jib crane
-
April -
Setting the Unit 2 generator access tube
-
April -
Chemical cleaning and pipe flushing equipment on the landside closure structure
-
April -
Voltage transformer checks for Unit 1 Cabinet 17 (photo courtesy of MWH)
-
April -
Installing the Unit 3 non-segregated bus above the generator access hatch (photo courtesy of MWH)
-
March -
Ohio River starting to recede below the powerhouse roof
-
March -
Powerhouse roof overtopped with 5.5 feet of river water
-
March -
Ohio River starting to overtop the powerhouse roof (photo courtesy of MWH)
-
March -
Protecting the distributor equipment in preparation of the river overtopping the powerhouse (photo courtesy of MWH)
-
February -
View of the Unit 1 completed shaft guards
-
February -
Boilermakers grinding the Unit 3 lower pier baffles
-
February -
Painting the Unit 3 bulb nose and cone joint 1
-
February -
Installing the gallery walkway
-
January -
Installing the gallery walkways in Unit 1
-
January -
View of the recreation area's picnic shelter
-
January -
Installing light poles on the north side of the substation (photo courtesy of MWH)
-
January -
Erecting scaffolding on top of a bulb nose (photo courtesy of MWH)