December - From left to right erecting the #2 & #1 unit draft tube liners
December - On the far right erecting the #2 section of the draft tube liner for the #3 unit
December - Gang form work in the equipment elevator area
December - Site view looking northwest
November - Aerial looking east
November - Aerial looking north
November - Aerial looking south with the spoil area at bottom of photo
November - Office trailer, preassembly and storage area
October - Inlet and turbine foundation work
October - Access road to the bottom of the pit with the flood gate at the upper left
October - Vibroflot on the left and auger on the right building stone columns
September - Aerial looking south
September - Draft tube liners awaiting installation
September - Turbine blades
September - Concrete placement in the inlet area
August - Dewatering piping going from the dewatering pit to the intake slab area.
August - Rebar in the inlet area
August - Oregon Iron Works Trashrack deliveries
August - Concrete mud slab in the draft tube liner area
July - Structural backfill in the draft tube area between PS-2 and PS-3
July - PS-5 Embedded Piping
July - Mud Mat for SC-4 and SC-7
July - Unit 1 bulb turbine housing and inner stay cone
June - Placing concrete in the intake slab area
June - Chilled water return settling pits and transfer conveyor
June - Aerial looking northwest during high water
June - Stone column erection
May - Form work for the #1 & #2 unit dewatering pit
May - Batch plant erection
May - Vibroflot building a stone column
May - Taking Engineering readings on #1 section of the draft tube liner in the preassembly area
April - Removing soil from bottom of the cell
April - Welding the draft tube liner in the preassembly area
April - Installing aerial warning spheres on the transmission line crossing the Ohio River
April - CPT testing on the stone columns installed on the riverside slope
March - Erecting transmission tower
March - Erecting the transmission tower
March - Production stone columns being installed
March - Erecting the concrete batch plant
February - Trimming the sheet piling in front of the power plant to grade
February - PVC conduit for electrical cable in trench ready to be encased in concrete at batch plant
February - Formwork, reinforcing steel and tower crane base ready for placement
February - Stone column installation
January - Truss frame for temp storage bldg A
January - Setting tangent section of sheet pile cut off wall using vibratory hammer
January - Placement of concrete for the draft tube erection building foundation
January - Aerial looking west with the overflow gate top center