December -
Hardfill placement continuation on the landside closure structure
-
December -
Receipt of the combined bearings support
-
December -
View of the powerhouse
-
December -
Preparations to move the shaft into temporary storage for pre-assembly
-
November -
Installation of shoring for the intake slab pours
-
November -
View of the tailrace and landside closure structure
-
November -
Landside closure structure hardfill placement
-
November -
View of the bulb turbine housing and formwork for second stage concrete
-
October -
Progress of the tailrace formwork looking landside
-
October -
Tailrace formwork and rebar
-
October -
Unit 1 intake water passage formwork and rebar
-
October -
Landside closure structure looking upstream
-
September -
Unit 1 bulb turbine housing upper pier installation
-
September -
Continuation of the tailrace formwork
-
September -
Setting Unit 1 stay cone
-
September -
Concrete embedment of the draft tube liners
-
August -
Lifting Unit 2 stay cone for installation 1
-
August -
Unit 2 formwork for the tailrace
-
August -
Setting Unit 1 bulb turbine housing
-
August -
Aerial view
-
July -
Setting of Unit 2 bulb turbine housing
-
July -
Pre-assembly work on the bulb turbine housing
-
July -
Construction of the tailrace wall
-
July -
Setting formwork for draft tube liner embedment
-
June -
Rebar and formwork for Unit 2 structural wall
-
June -
Hardfill for the hardfill trial placement
-
June -
Tower crane view of the powerhouse
-
June -
Grout curtain drilling in front of the intake block
-
May -
Alignment and welding of Unit 2 draft tube liners
-
May -
Setting Unit 2 draft tube liner
-
May -
Rebar installation for riverside intake wall
-
May -
Setting Unit 1 draft tube liner
-
April -
Bulb turbine housing arriving at the site
-
April -
Draft tube liner bracing installed
-
April -
Concrete placement and rebar for Unit 1 intake base slab
-
April -
Aerial view
-
March -
Pouring concrete for the powerhouse
-
March -
Centerline of tailrace (note arrow cast in structural slab)
-
March -
Placing formwork and rebar
-
February -
Overall view of the site
-
February -
Installation of rebar and embedded equipment
-
February -
Concrete pour for the central block
-
February -
Continuation of upstream excavation
-
January -
View of the site looking upstream
-
January -
Setting formwork for concrete placement
-
January -
Formwork for the tailrace base slab
-
January -
Aerial view