December -
Phase II compaction grouting
-
December -
Installing remedial stone columns on the 284 bench, land side
-
December -
Lower dewatering wells on the north end ready to be energized
-
December -
Predrilling for sheet piles for S-2 and starting sheet pile installation for S-2 on the river side
-
November -
S-2 drilling & grouting, 20 hr. days
-
November -
Emergency Floodgate Structure (EFS) spillway grouted
-
November -
Phase II ground improvement
-
November -
Flood gate installation, final grouting
-
October -
Excavating down to elev. 260
-
October -
Aerial photo taken October 25, 2011
-
October -
SPT Testing near southwest corner of power house
-
October -
Phase I stone column installation
-
September -
Sheet pile driving on the river side
-
September -
Redevelopment of south, lower dewatering wells, river side
-
September -
EFS construction
-
September -
Testing for the Phase II ground improvements
-
August -
EFS base slab construction
-
August -
Excavation starting at 260
-
August -
Low mobility grouting
-
August -
Aerial photo taken August 25, 2011
-
July -
EFS construction
-
July -
Stone column installation
-
July -
Pre-drilling for sheet pile driving
-
July -
First concrete placement for EFS
-
June -
Access road repairs
-
June -
Sheet pile driving
-
June -
Dewatering of cofferdam
-
June -
Aerial photo taken June 23, 2011
-
May -
Dewatering of the cofferdam
-
May -
100 year flood - May 2, 2011 - The Army Corps of Engineers, with agreement from the Federal Energy Regulatory Commission (FERC), directed AMP to flood the cofferdam.
-
May -
100 year flood
-
May -
100 year flood
-
April -
Access road flooding
-
April -
Rip rap lining
-
April -
Sheet pile cut off wall installation
-
April -
Stone column installation
-
March -
Demolition of Corps gate structure
-
March -
Sheet pile cut off wall installation
-
March -
Setting up for stone column installation
-
March -
Cofferdam excavation
-
February -
Demolition of the old Corps test gate structure
-
February -
The completed upper dewatering manifold, as seen looking west toward Smithland Dam and Illinois
-
February -
Primary excavation in progress, as seen looking north over the upper dewatering manifold
-
February -
Primary excavation is ongoing
-
January -
View of the fixed weir from the southwest corner of the cofferdam
-
January -
Construction of upper dewatering manifolds
-
January -
Test gate demolition
-
January -
Demolition of the test gate facility